Warning Edinburgh's North Bridge repair costs set to rise 'significantly'

The cost of repairs to Edinburgh's North Bridge have risen by another £1.2 million, it has emerged, as the council warned the project's budget is still set to increase 'significantly'.

Work to refurbish the bridge which links the Capital's Old and New towns began in 2018 after “multiple structural and safety defects” were identified.

But since then, more issues have been discovered with the historic crossing, as sections not inspected since its construction 130 years ago were found to be in need of major repairs.

READ MORE: Edinburgh's Christmas 'at risk' as time running out to award new contract

Last year the council approved an additional £25.8m for the increasingly expensive refurbishment, which took the total to £62m - more than double the originally agreed budget.

Now it's been revealed the total cost of the project has risen even further, with a report showing expenditure projections for the North Bridge are £8.3m this financial year, exceeding its allocation by £1.2m.

It said, however, that the overall increase in costs "is likely to be significantly more than this".

Council officials will consider the new estimates "as part of the budget proposals being brought forward in February 2023," the report added.

Quizzing officials at the finance committee on Thursday (January 26), Green group councillor Alys Mumford said: "It references the increase in costs is likely to be significant and that it will be part of the budget proposals.

"I wondered if there was any more information about what that increase is looking like at this time?"

Hugh Dunn, head of finance for the council, said: "The committee on the 7th of February will get an update on the capital programme and that will make reference to the increase costs that are estimated for North Bridge."

Whilst access for pedestrians and northbound traffic has been maintained, the major works have caused significant disruption to the city centre since repairs began.

The bridge is currently expected to fully re-open to traffic in June 2025, five years behind schedule.

Work being carried out by construction teams on the North Bridge includes a grit blast and repaint of all structural steelwork, improvements to pavements and underdrainage and installation of 'structural health monitoring systems'.

In addition, they will restore and repair the King's Own Scottish Borderers War Memorial, located on the east plinth of the bridge's south pier.

READ NEXT:

'No plans' to axe Edinburgh teachers after 'frightening' Glasgow proposals emerge

Edinburgh gardener and litter picker to stand for Greens in by-election

Former NHS nurse joins Edinburgh Council by-election race as Lib Dem candidate

Edinburgh's Portobello 'could be underwater in 50 years', expert warns

Surveillance abuse fear as Edinburgh council driver data collection plan paused

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.