Get all your news in one place.
100’s of premium titles.
One app.
Start reading
Newcastle Herald
Newcastle Herald
Matthew Kelly

'The owner is not a bull artist': new twist in old post office saga

Jerry Schwartz

Newcastle Post Office owner Jerry Schwartz has hit back at claims he is land banking the heritage jewel or otherwise deliberately delaying progress on its restoration, saying he is committed to his original vision for the site.

It follows criticism for the lack of visible restoration activity since he acquired the building in 2018, with Newcastle Herald columnist Paul Scott writing recently that the project's "inaction and unrealised announcements see the city's frustration morph into deep cynicism .. and the resultant belief that the PO's timely rebirth is little more than a cruel hoax".

The City of Newcastle spokesman recently said the council, "like many people in Newcastle, are losing patience with the owner of the site".

"It has now been two years since Dr Schwartz received development approval for the work and four years since he bought the old Post Office," the spokesperson said.

But Dr Schwartz says he remains committed to his original vision - an Indigenous cultural centre in the building's basement, shops and a cafe on the ground floor and a function centre on the top floor.

The Herald can reveal that builders are unlikely to be onsite until March 2024. This means a 2022 timeline that advertised the staged opening of the building, starting with the cultural centre in late 2023 and finishing with the conference centre in late 2025, will not be realised. However, it still may be possible for some parts of the project to be completed within the timeframe.

The newly opened Newcastle Post Office in May 1904.

Dr Schwartz said the delays, which have included the pandemic, had been as frustrating for himself as much as anyone.

"People should be glad the current owner is not a bullshit artist. I haven't deviated from my original plans, or put in an application to do something else," he said.

"My commitment has been there all the time. It's not in my interest to have a dilapidated building sitting there not doing anything. I don't land bank, I try and utilise what I can."

A new Newcastle architecture firm was enlisted in February following the retirement of the project's original architect.

A team of specialist consultants has also been engaged to prepare the outstanding reports as quickly as possible.

Almost every aspect of the work relating to state significant heritage building is time consuming and requires specialist skills and detailed investigation.

What's happened since 2018:

  • September 2018 - Jerry Schwartz buys the former Newcastle Post Office from the Awabakal Local Aboriginal Land Council for $3.5m
  • Dr Schwartz announces plans to create an Indigenous cultural centre, a conference facility and retail outlets.
  • March 2020 - Asbestos and lead paint removal completed
  • April 2021 - City of Newcastle approves a revised development application for the Newcastle Post Office following NSW Heritage assessment.
  • July 2022 - Dr Schwartz spends $18,000 to have 1.28 tonnes of pigeon droppings removed. Metal mesh is installed to pigeon-proof the building. Heritage consultants to inspect the building
  • December 2022 - Timeline for the staged opening of the post office is announced. Indigenous museum late 2023, ground floor retail late 2024 and first floor conference centre late 2025
  • February 2023 - New architects engaged to complete reports and drawings needed to apply for a construction certificate

Specific challenges relate to the installation of services and working with the existing building fabric.

Jerry Schwartz visiting the building 2021. Picture by Max Mason-Hubers

Dr Schwartz said he had been assured that every effort was being made to deliver an architectural package by October.

The project will then need to be referred to the heritage branch of the Department of Environment and Heritage before it can be submitted for certification.

With the Christmas-New Year shutdown factored in, it is unlikely that work will commence before March 2024.

In the meantime, an emergency application is being made to replace the building's roof, which is leaking.

Dr Schwartz paid $18,000 to have 1.28 tonnes of pigeon poo removed and metal mesh installed in August 2022.

He also paid $100,000 to replace the building's original copper drain piping that was stolen.

WHAT DO YOU THINK? Join the discussion in the comment section below.

Find out how to register or become a subscriber here.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.