Get all your news in one place.
100’s of premium titles.
One app.
Start reading
Tom’s Hardware
Tom’s Hardware
Technology
Matthew Connatser

SK hynix to spend $90 billion to build 'world's largest mega fab complex' — first fab operational in 2027

SK Hynix Fab.

SK hynix will begin constructing its mega fab complex called the Yongin Semiconductor Cluster in March 2025, with a completion date estimated in 2046 (via ComputerBase). The complex, which includes four separate fabbing facilities, will cost at least 120 trillion Korean won or just shy of $90 billion. Once completed, it will likely be the largest fab complex in the world, and there's even more room in the broader area for companies like Samsung to build other facilities.

SK hynix, one of South Korea's most notable semiconductor firms, has been planning its quadruple fab complex in the Gyeonggi Province next to Seoul for several years. The construction site is currently being prepared, and apparently, a third of those preparations have been completed, which likely means construction will start as planned in March 2025. 

Although the completion date for the entire complex is set for 2046, that doesn't mean individual fabs won't be online before then. Back in September, SK hynix said the first of the four fabs would be completed in 2027, or roughly two years after construction starts. We don't know what will be produced at this first fab, but since SK hynix produces RAM and NAND chips, so it will likely be one of those. HBM may be a prime candidate given the demand for it in server-class and AI-oriented hardware.

If each fab takes two or three years for construction, it raises questions about why the complex will take 19 years instead of somewhere between eight and 12. However, building so many fabs in such a small area may pose unique challenges regarding building support facilities (like water treatment) and logistics. Schematics for the complex show that the four fabs themselves only take up about half of the entire complex, so quite a few other buildings are planned as well.

Once completed in 2046, the mega fab complex will probably be the world's largest, and Fab 1 is also apparently set to be the world's largest three-story fab when it's done in 2027. The wider Gyeonggi area will also host other chip-making facilities from companies like Samsung. SK hynix and Samsung are already envisioning the construction of 13 more fabs and three R&D facilities in Gyeonggi. This project is backed by a $463 billion budget, funded mainly by Samsung and partners.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.