Inland Rail project build blows out to $31.4 billion

Catherine King, Dr Kerry Schott and Katy Gallagher speak on the proposed Inland Rail project. Photo: AAP

A freight line from Melbourne to Parkes will take priority in an overhaul of the Inland Rail project, after an independent study found a massive cost blowout under the coalition government.

Inland Rail is a 1700km line intended to link Melbourne and Brisbane via regional Victoria, NSW and Queensland.

When finished it is expected to reduce truck volumes across at least 20 regional towns, ease congestion on major highways, cut carbon emissions and provide a reliable network for producers, farmers and businesses.

A study released on Thursday has found the project, estimated to cost $9.3 billion five years ago, has blown out to $31.4 billion.

Report author Kerry Schott said the section between Melbourne and Parkes could be completed by 2027, but there was no indication of the timing of the project beyond this.

Dr Schott said while progress was being made in terms of NSW approval processes, Queensland’s work was “well behind”.

She would not “hang her hat” on the 2030s estimate for the Queensland leg of the project.

Transport Minister Catherine King said it would take a lot of work to get the project back on track.

“The previous government began this project with no idea where the rail line would start in Melbourne, and where it would finish in Brisbane, or how it would interact with towns, communities and the natural environmental along the route,” she said.

Dr Schott found the government-owned Australian Rail Track Corporation did not have the expertise to manage the project, recommending Inland Rail be made a subsidiary company to allow it greater control of project management and approvals processes.

But the academic and Albanese government insist the project should go ahead.

“As it stands, Inland Rail is expected to accommodate and drive a modal shift of 200,000 trucks a year to rail, and this will bring significant benefits in terms of supply chain efficiencies, safety, environmental and congestion reductions,” Dr Schott said.

Ms King said the government had accepted in principle or in full all of Dr Schott’s recommendations, which would lead to “sweeping changes” to the project.

An independent cost estimator and value engineer will be appointed to undertake detailed assurance work.

Experts would also be added to the ARTC, with recruitment under way for an Inland Rail CEO.

“Inland Rail does remain an important project to meet Australia’s growing freight task, improve road safety and to help decarbonise our economy, but we have been left with one almighty mess,” the minister said.

Finance Minister Katy Gallagher, who is a shareholder minister in the project, said it would take 18 months to work through detailed costings.

About $2 billion has been spent so far.

– AAP

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.