Get all your news in one place.
100’s of premium titles.
One app.
Start reading
Daily Mirror
Daily Mirror
National
Rachel Alexander & Tim Hanlon

Grieving mum forced to live in home where daughter died after swallowing a button battery

A grieving mum says she is desperate to move house amid a long-standing dispute over the electricity supply at her new property.

Stacy-Marie Nicklin, from Stoke-on-Trent, has been waiting since October to move out of the home where her two-year-old daughter Harper-Lee Fanthorpe swallowed a button battery in May 2021.

But despite packing her entire life up, as well as forking out several times for removal men and taking unpaid days off work, the move has been repeatedly called off.

With her current house full of painful memories, she wants to move to one of five nearby new-builds, but this has been delayed by a stand-off over a trench where the utilities connections go.

Harper-Lee Fanthorpe tragically swallowed a button battery in May 2021 (Stoke Sentinel)
Two-year-old Harper-Lee (Stoke Sentinel)

Stacy, 37, told StokeonTrentLive that the situation is taking a heavy toll on her as well as daughters Kylie, 14, and 19-year-old Jamie-Leigh.

She said: “After Harper died, I tried but just couldn’t carry on living here, because of all the painful memories. This living room is where Harper was bleeding from the mouth as the battery burned her insides.

"I couldn’t take being here again on her birthday or at Christmas, so we looked for somewhere new.

“We were all set to move months ago, and then just as we were about to go they’d tell us it had been delayed because of something to do with the electrics. But every time I went past the house, there was no sign of any work being done.

"In the meantime, we were living out of boxes and I was having to take days off work, only to be let down at the last minute.”

In September last year, Staffs Housing, which is the housing association behind the scheme, had reportedly told Stacy it was hopeful the tenancies could begin in October, 2022.

Stacy said her present home is full of painful memories (Pete Stonier / Stoke Sentinel)

Then, in later messages, it warned that there were “a few bits that needed to be completed” and said the handover date might be December 2.

But on December 1, a problem arose around one piece of work still outstanding, and left everything up in the air.

SAS Associates, which was due to complete the electrical connections, reportedly says it was told by the city council that a complaint had been made about the length of the pedestrian diversion - which it says the council had previously approved.

The contractor says it said it would make relevant changes - including replacing signs that had apparently been stolen - but was told the “change to traffic management” couldn’t be approved until January.

The works were closed down and the hole filled. And SAS says that its revised bill for opening up the hole, making the changes to diversion, and finishing the work, was rejected by the developer, Arthur Roberts & Sons Ltd.

A spokesman for Kamar Developments, the sub-contractors on site, said: “We want people to be in there, as soon as possible because I want to be out, I want the job finished.

“I can assure you we’ve done our utmost to get this sorted but it’s the independent connections provider, SAS Utilities. They’ve turned around and said ‘We’re not coming back until you’ve paid this variation in full,’ which obviously at the moment I’m not prepared to do.

There is a delay to moving into the new property (Pete Stonier / Stoke Sentinel)

“Don’t get me wrong, the houses are done, they’re finished. But the problem is we can't get the completion certificates sorted because I can’t do the inspection and testing until the electricity is connected.”

A Kamar Developments spokesman said the bill received from SAS is to the tune of £16,000. SAS said the initial sum for the final connection work had been set back in September at £9,000 as long as there were no variations.

But it says the extra work as a result of the complaint in December means that the job has changed, and “under our terms and conditions works cannot be undertaken until variations are agreed”.

With work now at a standstill, Stacy said: “I would just beg them all to sort this out. We can’t expect them to have known the impact this is having, but it’s just dragging our nightmares out for longer and longer.

"We’re so desperate to move and get out of this house, we’d dig the hole ourselves if we needed to.”

The city council, which manages the housing waiting list, said it is in touch with Staffs Housing over Stacy’s move.

Tim Sheail, Director of Housing Services at Staffs Housing, said he had every sympathy with Stacy and the other families affected, adding: “Dividy Road is a new development of five houses which are being built by an independent contractor.

"The project has been significantly delayed because of problems with utility connections which are beyond our direct control.

“We really sympathise with Stacy and the other residents who were due to move into their new homes last year. We understand how frustrating the delays are and realise how difficult this has been.

"Our Housing Team has been in regular contact with all future residents and we will continue to do all we can to support them.”

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.