Explained | India’s coal shortage and its effect on power supply

As per the latest data, coal stocks at more than 100 thermal power plants in India have fallen below 25% of the required stock (critical mark). In more than 50 thermal plants, the stock has fallen below the 10% mark, leading to States seeking additional coal supplies from India’s sole coal producer Coal India Ltd (CIL). Seventy per cent of India’s power demand is met by thermal power plants, which are mostly powered by coal.

Central Electricity Authority (CEA) data shows that as of April 19, 2022, India’s power generation via thermal plants using domestic coal stood at 182.39 GW with an average of 34% coal stock in them. Meanwhile, 16.73 GW was generated by power plants using imported coal with an average coal stock of 34%. Nine thermal plants with the capacity to generate 3.56 GW are currently non-functional.

Of the 173 thermal power plants, 85 plants fired by domestic coal have less than 25% stock while 11 plants running on imported coal have hit critical levels.

Why does India face a coal shortage?

The biggest reason for coal shortage is the increasing power demand. In 2021, demand increased to 124.2 BU per month from 106.6 BU per month in 2019. In 2022, the demand has further increased to 132 BU.

In October 2021, when India faced a major coal crisis due to shipping delays with stocks dropping to just four days, the Centre’s core management team (CMT) analysed the reasons for the shortage in supply.

The CMT stated that the heavy rains in coal mining areas like Gujarat, Punjab, Rajasthan, Delhi and Tamil Nadu had resulted in lesser coal production. Moreover, prior to the monsoon season, there was inadequate coal stock build-up in most thermal plants, pushing them below critical levels.

The Centre also stated that there was a 43.6% reduction in power generation from imported coal, which led to extra demand of 17.4 MT of domestic coal, further depleting coal reserves.

What is CIL doing to mitigate the shortage?

On Tuesday, CIL stated that it had raised its supplies to thermal power stations by 14.2% during the first half of April 2022, compared to the same period last year. Coal generation has hit 1.64 million tonnes (MTs) per day compared to 1.43 MTs in 2021.

The company added that it had raised its production to 26.4 million tonnes during the first half of April, achieving 27% year-on-year growth. Additionally, 8.75 MTs of coal will be made available to state and Central generating companies vial rail till May 31, 2022, stated CIL.

How will coal shortage affect power supply and cost?

As per Fitch, the daily electricity deficit in India has increased from 0.3% to 1% in April 2022. This has led to an 85% increase in the price of electricity traded on Indian exchanges from an average of Rs 3/kWh to Rs 8.23/kWh in March. To regulate prices, CEA has capped short-term power exchange rates to Rs 12/kWh. Fitch further estimates that low coal supplies will not allow National Thermal Power Corporation (NTPC) to increase its plant load factor — its power output with respect to its fuel — more than 70.7%. This was the limit NTPC had increased its load to in 2021, up from 66% in 2020.

The peak in demand has been met with load shedding, planned outages by States like Andhra Pradesh, Gujarat, Maharashtra, Jharkhand, Bihar, Haryana and Uttarakhand. Since April 1, Jharkhand has been facing an average supply shortage of 10-12%, followed by Andhra Pradesh (10%), Uttarakhand (8-10%), Madhya Pradesh (6%) and Haryana (4%).

How does the Centre plan to fix the coal crisis?

The Centre has allowed States to use its captive coal reserves up to 25% to meet growing domestic demand. It has also allowed generating companies to blend imported coal up to 10% to ease the burden on CIL. While the Centre is mulling shoring up imported coal stock, higher coal costs make it difficult.

In 2020, Centre had passed mining reforms to end CIL’s monopoly on India’s coal manufacturing. The law allowed commercial mining in coal sector with 50 blocks to be offered immediately. It also allowed any party to bid for coal mines instead of only captive consumers (i.e companies which use coal for running their businesses).

The law also incentivised early coal production with rebate in revenue share and promised Rs 50,000 crore investment for diversifying CIL’s operations. The law has, however, run into severe Opposition from States — especially mineral-rich states like Jharkhand, Bihar —citing that this will have an adverse impact on a large tribal population and forests. The case is pending in the Supreme Court.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.