Deal with state, federal government would give Lexington until 2030 to finish court-ordered sewer im

Lexington’s city council is expected to vote March 21 on a deal to give the city four more years to finish court-ordered improvements to its sanitary sewer system. In 2011, the U.S. Justice Department, working with the EPA and the state, mandated the improvements and set an end date of 2026. Division of Water Quality Director Charlie Martin has been with the city since 1999.

“It's fairly well known that when I came here that they had reoccurring sanitary sewer overflows that would – manholes that would pop every time it rained. We've come a long way since that time, and we don't have a lot of the overflowing manholes that we had in the past.”

Martin said if the council approves the deal, he’s confident the state and federal governments will accept it. He said the original estimate for improvements to the city’s sanitary sewer system was $600 million and he still hopes the final tally will be less.

“Currently, we projected that we would have spent $470 million; by this point, our actual expenses are $372 million.”

Martin acknowledged multiple sewer rate increases were needed to pay for the improvements. Lexington Environmental Quality & Public Works is a financial supporter of WEKU.

** WEKU is working hard to be a leading source for public service, and fact-based journalism. Monthly supporters are the top funding source for this growing nonprofit news organization. Please join others in your community who support WEKU by making your donation.

Sign up to read this article
Read news from 100’s of titles, curated specifically for you.
Already a member? Sign in here
Related Stories
Top stories on inkl right now
One subscription that gives you access to news from hundreds of sites
Already a member? Sign in here
Our Picks
Fourteen days free
Download the app
One app. One membership.
100+ trusted global sources.